This website uses cookies

This website uses cookies to improve user experience. By using our website you consent to all cookies in accordance with our Cookie Policy.

English
Deutsch

Vision & Genesis

The vision: Berlin's most beautiful pedestrian zone

In 2018, HGHI laid the foundation stone for the revitalisation of the 250-metre-long pedestrian zone Gorkistraße, existing since 1972, including the Tegel-Quartier and the market hall.

"We are fascinated by the idea of completely redefining Gorkistraße as an urban shopping street and revitalizing the aging location. Our aim is to create Berlin's most beautiful pedestrian zone that can hold its own against any established shopping centre", says Harald Gerome Huth, owner and managing director of HGHI Holding GmbH.

The project is one of the first central refurbishments of a complete shopping street in Germany.

The revitalization plans include a fundamentally redesigned shopping and experience world with the expansion of retail and office space. The heart of the new pedestrian zone is a completely redesigned natural stone façade with façade relief, which will be added to the existing building fabric and constructed as a new construction.

50,000 sqm Retail space


100 Shops & brands


12,000 sqm Office space


Market hall with 40 booth


600 lots car parking, 200 lots bike parking

Another important part of the project development is the redesign of the traditional market hall, which looks back on a 100-year history.

The preservation of the long-standing tradition as well as the simultaneous creation of a modern and contemporary ambience have the highest priority in the renovation measures. The market hall has been moved to the ground floor of the former Hertie house with almost all of the old tenants until its final location in the southern part of the Tegel Center. Further information on the market hall can be found at www.markthalle-tegel.de.

With the anchor tenant Karstadt as well as Deichmann, Rewe, DM and many other brands, visitors will in future be offered a varied mix of products.

"We expressly welcome the HGHI building project. The comprehensive modernization and expansion of the area means a significant increase in attractiveness for the entire district. Tegel will be noticeably upgraded as a result and will in future combine the already diverse gastronomy offers and excursion destinations with a modern and urban world of experience and shopping. Not only those who shop there will benefit from the opening, but also the entire retail location of Tegel. We are looking forward to this", says District Mayor Frank Balzer (CDU).

Before / After

Current Construction Progress

May - July 2019

Concreting work is progressing in the south section. In the basement, 80 percent of the floor slabs and 50 percent of the walls are concreted. This work is expected to be completed by July. The ground floor will then be concreted.

In the north section, the shell of the 3rd floor is almost completed, and the roof of Karstadt has been sealed. Steel platforms were installed on the roof. This is a technical substructure for ventilation units and recoolers. In the next step, the Karstadt building will be lavishly scaffolded in order to be able to erect the second level of the steel towers on the roof. 

April 2019

On the roof of Karstadt, work has begun on the assembly of the steel platforms. In addition, the shell of the 3rd upper floor in the north section (new building) will be completed. The roof waterproofing will be finalised by the end of April.

March 2019

The structural shell of the 2nd upper floor in the north section (new building) has been completed to 85 %, two indoor escalators have been installed. The interior fittings in the Karstadt rental area and the extension of the building services on all floors are making further progress. The roof sealing has almost been completed and essential components of the cooling and heating system have been installed. In addition, the design of the natural stone facade in the central part of the Karstadt building is taking shape.

January - February 2019

January on the construction site of the new pedestrian zone Gorkistraße / Tegel-Quartier was all about concrete: The slab above the ground floor in the northern building element and the slab to the basement in the southern building element were completely concreted. The finishing work in the interior of the Karstadt area is progressing further, and escalators were installed for this purpose.

In February, the excavation pit was completed and handed over in the eastern and western parts of the southern section. The structural work for the construction of the first upper floor has begun. In the north section of the Karstadt site, waterproofing and facade design work is continuing. The design of the natural stone facade in the first section from the former Berliner Bank to the Karstadt main entrance is expected to be completed by the end of March. From mid-March, first the eastern and then the western steel construction tower will be erected there.

Archive Contruction Progress

  • Archive 2018

    Archive 2018

    November / December 2018

    Structural work on the south section began in November. Among other things, the first foundations were concreted and the first parts of the exterior walls were constructed. Work on the excavation pit is progressing and completion is scheduled for spring 2019. The expansion of the technical building equipment (refrigeration and heating technology, ventilation and electrical systems) in the north section is progressing further, and the escalators will be installed on the Karstadt site by the end of the year. The drywall construction and sealing of the roof areas have also started.

    October 2018

    In the south section, the groundwater level was lowered to allow civil engineering work to begin. In the north section, the facade design of the Karstadt area on Gorkistraße continues to progress. After completion of the so-called Pfosten-Riegel facade, the natural stone work was started. In addition, the extension from the first floor to the third floor has been finalised.

    September 2018

    After completion of the excavation pit, preparations for the shell construction work (anchoring of the walls, ground drilling with a view to explosive ordnance disposal, completion of the excavation work (excavation and removal of building rubble and soil materials). In the north section, the structural alterations will be carried out up to the first floor (construction of the ceiling cut-outs for escalators and lift shafts) and the drywall work as well as the Expansion of technical building equipment (TGA) commenced.

    August 2018

    In the north section, further work is being carried out on the interior and exterior facades of the building (installation of windows, sealing of ceilings, etc.)

    July 2018

    In the north section of the basement, the floor slabs were concreted and the first columns for carrying the future ceiling on the ground floor are set up. For further work in the pit the construction and installation of a construction crane was carried out. On the parking deck the ceiling on the third floor was concreted. In the South section, the excavation work of the building pit was accomplished. For this purpose, the sides of the excavation pit were covered and obstructed. (sand slide protection).

    June 2018

    The substructure for the natural stone elements on the façade is being installed. In addition, work will begin on increasing the floor level of the parking area. The first of four floor slab sections is concreted. On 8 June 2018, the HGHI lays the foundation stone for the new pedestrian zone. Further information can be found in the press release on the laying of the foundation stone.

    May 2018

    The glazing of the façade continues and the first bricklaying work begins in the basement. The excavation pit is handed over by the civil engineer to the structural engineer, so that he can start the preparatory work for concreting the floor slab. In the Karstadt tenant area, the first shell construction works are carried out, the outer walls on the north facade are bricked and the concrete surface on the roof is renovated and sealed.

    April 2018

    Let there be light! In keeping with the surprisingly springlike weather in April, glazing begins. This is not the only reason why the future Karstadt area is slowly becoming concrete. You slowly get a first impression of what the entrance to the department store will look like.

    March 2018

    It gets high in March: In the 2nd floor several safeguards for the workers are installed. But it also goes at least as deep in the other direction: The core drillings for the concrete cutting work on the elevators are being prepared. Negative temperatures and snow are not necessarily helpful.

    February 2018

    In February, the core is gutted, stripped and excavated. A part of the roof is temporarily opened so that the men can easily transport their building materials to the open construction site by crane. Slowly the façade on Gorkistraße takes shape.

    January 2018

    A large heap of accumulated rubble is disposed of from the parking level on the 2nd floor. In addition, the excavation pit of the new northern building will be excavated. The cold Berlin winter doesn't necessarily make both things easier for the men of construction. Since January, the future Spielothek can also look forward to the start of the installation of the ventilation system. Because the winter is persistent and the installation of the ventilation system is a costly affair, the games library also receives a temporary rain cover.

  • Archive 2017

    Archive 2017

    December 2017

    In the southern part of the Tegel quarter, the former medical center at Grußdorfstraße will be demolished by the end of March 2018. The bored pile work for the southern part is expected to start at the beginning of March. In the northern part of the Tegel quarter, the stairway heads are cut to fit exactly where the old TC letters were placed. In the area of new construction north, dewatering was activated.

    November 2017

    In the northern part of the former Tegel Center and along Gorkistraße, the demolition of the facade and gutting work on the existing building of the shopping centre took place in the last weeks and months. The shell construction work, such as column reinforcements and supports as well as foundation underpinning using the high-pressure injection method (HDI) have also already started. The subsoil has been improved and replaced by earth concrete, a mixture of soil and cement slurry. The old multi-storey car park on Buddestraße/Bernstorffstraße was completely demolished and the excavation pit for the new building was created. In the southern part of the complex, the demolition building was gutted and the interim area of Tchibo in the former Hertie house has been completed.

    August 2017

    The building permit for the conversion and extension of the pedestrian precinct Gorkistraße / Tegel-Quartier was issued by the Berlin-Reinickendorf district authority on 2nd August 2017.

    July 2017

    Due to construction measures, the Buddestraße in Tegel will be closed completely from July 24th 2017 until August 6th (calendar week 30 & 31), leading to traffic-related constraints. The following bus lines are affected by this: Bus 124, 125, 133, 220, 222, N22, N24, N25, N33. Apart from that, the mentioned bus lines run on their usual route. Diversions for the bus lines will be set up.

Videos

© HGHI Tegel Quartier GmbH
Mendelssohn-Palais
Jägerstraße 49/50
D-10117 Berlin - Germany

Tel: +49 30 804 98 48-0
Fax: +49 30 804 98 48-11

E-Mail: hghi-tegelquartier@hghi.de
Internet: www.hghi.de